Five Star Scaffolding Pty Ltd
ABN 70 130 008 212
61 Long Street, Smithfield NSW 2164
(02) 9632 3466

Monthly Inspection

Project Details


30 Day (Monthly Inspection)
Other Works - mention in Notes below
 

Scaffold Details

The scaffold described below has been erected in accordance with AS 4576 - Guidelines for scaffolding, AS 1576 (1-6) - Scaffolding, AS 1577 - Scaffold planks, Work Health and Safety (managing the Risks of Falls at Workplaces) Code of Practice 2015, Safe Work Australia - Guide to Scaffolds and Scaffolding. The scaffold described below is suitable for its intended purpose only.
All Hop-up’s can only be installed following the removal of the form ply deck below. The Principal contractor must ensure all falls are managed in the interim by either installing adequate edge protection or ensuring the ply is formed to the perimeter scaffold internal standards.
Hop-Ups are to be loaded to maximum capacity of 225Kg
Simultaneous loading permitted as per Scaffold Design

Yes No N/A

LIGHT 225 KG
MEDIUM 450 KG
HEAVY 675 KG
SPECIAL DUTY

East Elevation
West Elevation
North Elevation
South Elevation
Lift Shaft
Base
Bird Cage
Roof
Void
Loading Platform
Whole Level
Whole House




Signatures

I acknowledge that I have read and understood and agree with the Handover Certificate Terms and Conditions. I have fully understood the Duty Category of the work platforms. Any breach of the Handover Certificate Terms and Conditions may result in an infringement of "Decommission of Scaffold Notice" being issued. Any breach of the Handover Certificate may lead to injury or death.